Shimul - Row House ( Construction Updates as on as on 20th NOVEMBER 2017 )




Shimul Row House

Plaza, Deck area brick work WIP.

Shimul Row House

Gallery, Roof slab completed.

Shimul Row House

Club House, Roof slab WIP.

Shimul Row House

SHIMUL - 3, Inside and Outside plaster WIP

Shimul Row House

SHIMUL - 1, Inside flooring WIP

Shimul Row House

SHIMUL - 1, Out side Completed.

Shimul Row House

SHIMUL - 1, Inside plaster completed

Shimul Row House

SHIMUL - 1, Inside plaster completed

Shimul Row House

SHIMUL - 2,Inside and Outside plaster WIP

Shimul Row House

SHIMUL - 3, Inside and Outside plaster WIP

Shimul Row House

SHIMUL - 4, Inside and Outside plaster WIP

Shimul Row House

Club House, Foundation WIP.

Shimul Row House

Gallery, Foundation Completed.

Shimul Row House

Plaza, Deck and Feature wall Foundation WIP.